Planned maintenance percentage calculator

Planned maintenance percentage is the share of your maintenance hours that were planned rather than reactive. It is the clearest single measure of whether a maintenance team is running the equipment or the equipment is running the team.

PMP = Planned maintenance hours ÷ Total maintenance hours × 100

Work scheduled in advance with parts and labor identified

Show the assumptions
Formula
PMP = Planned maintenance hours ÷ Total maintenance hours × 100

Hours, not work order counts. Counting jobs treats a two-minute reset and a two-day rebuild as equals, and reactive work skews heavily towards the short jobs.

Planned does not mean preventive. A corrective repair that was scoped, parted and scheduled for next Tuesday is planned work. Work that started because someone walked past a leak is not, even if it was necessary.

Planned maintenance %

Prefilled with an example. Change any number and the result updates.

How to calculate Planned maintenance %

PMP = Planned maintenance hours ÷ Total maintenance hours × 100

Hours, not work order counts. Counting jobs treats a two-minute reset and a two-day rebuild as equals, and reactive work skews heavily towards the short jobs.

Worked example

  • Planned maintenance hours 640 hrs
  • Total maintenance hours 1,000 hrs

Planned maintenance % = 64.0%

Reading the result

Planned does not mean preventive. A corrective repair that was scoped, parted and scheduled for next Tuesday is planned work. Work that started because someone walked past a leak is not, even if it was necessary.

Benchmarks

80% to 90% planned is the range commonly cited for a mature program. Below 50% the team is effectively reactive, whatever the PM schedule says on paper.

Planned maintenance % questions

What is the difference between planned and preventive maintenance?

Preventive means the work was triggered by a schedule or a meter reading before anything failed. Planned means the work was prepared before it started, whatever triggered it. A breakdown repair can be planned work if it was scoped and scheduled rather than attacked immediately.

Should I measure in hours or work order counts?

Hours. Reactive work is dominated by short interventions, so a count-based figure flatters a reactive team. The hours are also what you actually pay for.

Move work from reactive to planned

UpKeep records the work, the hours and the failures this metric depends on, so Planned maintenance % is a report rather than a spreadsheet exercise.